NPV and IRR in Excel (Plus XNPV, XIRR and Payback Period)

Should you buy the new van, the machine or the software? NPV and IRR answer that by putting future cash in today’s money. Excel has a function for each, but NPV has a trap that gives the wrong answer in most spreadsheets. This guide walks through one small-business investment: NPV done right, a manual check, IRR, payback and discounted payback, and XNPV and XIRR for real dates, with a free calculator.

NPV and IRR in Excel for a delivery van: =NPV(C3,C6:G6)+B6 gives an NPV of 2,066.24 at a 10.0% hurdle rate, an IRR of 11.57% and a payback of 3.60 years.
NPV, IRR and payback for one investment, side by side.

NPV, IRR and payback in one minute

MeasureQuestion it answersRule of thumb
NPV (net present value)How much value does the project add, in today’s money, after earning the hurdle rate?Accept if NPV > 0
IRR (internal rate of return)What return does the project earn?Accept if IRR > hurdle rate
Payback periodHow many years until the cash comes back?Shorter is safer; ignores the time value of money
Discounted paybackHow long until the discounted cash comes back?Must be within the project’s life

The hurdle rate (or discount rate) is the return you need to justify the risk: your cost of borrowing or the return you could get elsewhere. This example uses 10%.

Free download: Get the NPV, IRR and payback calculator (.xlsx). It has the Project sheet, a Dated sheet for XNPV and XIRR, and a How It Works sheet. Works in Excel 2010 and later, Microsoft 365 and Excel for the web.

Step 1: Lay out the cash flows by year

Put the years in a row (0 to 5) and the cash flows underneath. Year 0 is today: the 50,000.00 van, entered as a negative number. Years 1 to 5 are the extra cash the van brings in after running costs and tax, and year 5 includes what you expect to sell it for. Use cash, not profit: depreciation is not a cash flow, so leave it out (it only matters through its effect on tax).

Excel cash flow layout with a 50,000.00 investment in year 0, inflows from 12,000.00 to 15,000.00 in years 1 to 5 and a 10.0% discount rate.
Year 0 is the investment; years 1-5 are the inflows.
Checkpoint: Cash flows -50,000.00, 12,000.00, 14,000.00, 15,000.00, 15,000.00 and 13,000.00, and 10.0% in C3.

Step 2: Calculate NPV

=NPV(C3,C6:G6)+B6

Excel’s NPV function assumes the first value in the range is one period away. That is right for years 1 to 5, so they go inside the function. The year-0 investment happens today and is already in today’s money, so it is added outside, undiscounted.

Excel NPV formula =NPV(C3,C6:G6)+B6 returning 2,066.24 for the delivery van project.
Discount years 1-5, then add year 0.
Checkpoint: NPV at 10% is 2,066.24. The van covers the 10% hurdle rate and adds 2,066.24 of value in today’s money, so the decision cell says Accept.

Step 3: Check it, and avoid the common mistake

Rows 8 to 10 build the same answer by hand. The discount factor for each year is:

=1/(1+$C$3)^B5

Each cash flow times its factor gives the discounted cash flow, and their sum in C13 is 2,066.24, the same as the NPV function. Now the mistake almost everyone makes:

FormulaResultWhy
=NPV(C3,C6:G6)+B62,066.24Correct: year 0 is not discounted
=NPV(C3,B6:G6)1,878.40Wrong: every cash flow, including the investment, is pushed one year later

The wrong version is exactly the right answer divided by 1.1. The gap grows with the size of the investment and the rate, and it can turn a good project into a bad one.

Excel discount factors and discounted cash flows summing to an NPV of 2,066.24, next to the common mistake =NPV(C3,B6:G6) that returns 1,878.40.
The manual check proves the NPV; including year 0 in NPV() does not.

Step 4: Find the IRR

=IRR(B6:G6)

Unlike NPV, IRR takes the whole range, year 0 included: it needs at least one negative and one positive cash flow. IRR is the discount rate at which NPV is exactly zero, which C16 proves by recalculating NPV at the IRR.

Excel IRR formula =IRR(B6:G6) returning 11.57%, with NPV at the IRR equal to zero.
IRR is the rate that brings NPV to zero.
Checkpoint: IRR is 11.57%, above the 10% hurdle rate, which agrees with the positive NPV.
IRR returns #NUM!? Excel could not find a rate. Check that the range has both negative and positive values. For unusual cash flows, give a starting guess: =IRR(B6:G6,0.1). If the cash flows change sign more than once, there can be two IRRs; trust NPV instead. Avoid hiding the error with IFERROR (see IFERROR vs IFNA).

Step 5: Payback and discounted payback

Row 7 is the cumulative cash flow, =SUM($B$6:B6) filled right. It stays negative for three years (-9,000.00 after year 3) and turns positive in year 4. Payback is the full years plus the fraction of the next year needed to cover the shortfall:

=IF(G7<0,"Not recovered",COUNTIF(C7:G7,"<0")+(-INDEX(B7:G7,COUNTIF(C7:G7,"<0")+1))/INDEX(B6:G6,COUNTIF(C7:G7,"<0")+2))
  • COUNTIF(C7:G7,"<0") counts the years still negative: 3.
  • INDEX(B7:G7,3+1) is the cumulative shortfall after year 3: 9,000.00.
  • INDEX(B6:G6,3+2) is year 4’s cash flow: 15,000.00.
  • So payback = 3 + 9,000 / 15,000 = 3.60 years. The IF returns Not recovered if the project never pays back (see how to build an IF formula).

The same formula on the discounted rows 9 and 10 gives the discounted payback: 4.74 years. It is longer because later cash is worth less today.

Excel payback period of 3.60 years and discounted payback of 4.74 years calculated from cumulative cash flow rows.
Payback from the cumulative rows.

Step 6: XNPV and XIRR for real dates

NPV and IRR assume equal periods. Real projects rarely work that neatly: on the Dated sheet the van is bought on Jan 15, 2026 and the yearly cash arrives each March 31, starting in 2027. Use the date-based versions:

=XNPV(Project!C3,B5:B10,A5:A10)
=XIRR(B5:B10,A5:A10)

Note the difference in how the range works: XNPV discounts everything to the first date, so the investment stays inside the range and is not discounted. There is no need to add it separately.

Equal yearsActual dates
Net present value2,066.24 (NPV)1,045.94 (XNPV)
Rate of return11.57% (IRR)10.75% (XIRR)

The first inflow now arrives after 14.5 months instead of 12, and every later one is 2.5 months later too, so both results drop. For monthly or irregular cash flows, XNPV and XIRR are the honest numbers.

Excel XNPV and XIRR with actual dates: XNPV 1,045.94 vs NPV 2,066.24 and XIRR 10.75% vs IRR 11.57%.
Real dates lower both NPV and the return.
Ready-to-share test: Change the discount rate in Project!C3 to 12%. NPV becomes (538.98), the decision changes to Reject, discounted payback shows Not recovered, and the IRR stays at 11.57%: the project’s return did not change, only your required return did. Change it back to 10% when you are done.

Where the cash flows come from

The calculator is only as good as its inputs. Build the yearly cash flows from a forecast (see the 12-month cash flow forecast), include the resale value, and use after-tax cash. If the purchase is financed, keep the loan out of the project cash flows and compare the IRR with the loan rate instead; the loan amortization schedule gives you the payments. For the tax effect of the asset, use the depreciation schedule, and to see how much you must sell each year to cover fixed costs, use break-even analysis.

Frequently asked questions

Why is my Excel NPV different from my calculator?

Most likely the year-0 investment is inside the NPV function, so it is discounted by one period. Use =NPV(rate,year1:yearN)+year0.

What is the difference between NPV and XNPV?

NPV assumes equal periods and discounts the first value by one period. XNPV uses actual dates, discounts to the first date and does not discount the first value.

What is the difference between IRR and XIRR?

IRR assumes equal periods; XIRR uses the actual date of each cash flow. Use XIRR when cash flows are monthly, irregular or do not start exactly one period after the investment.

Which is better, NPV or IRR?

NPV, when you compare projects of different sizes or the cash flows change sign more than once. IRR is easy to explain as a percentage. Use both and check that they agree with your hurdle rate.

How do I calculate payback period in Excel?

Add a cumulative cash flow row. Payback = years with a negative cumulative total + the remaining shortfall divided by the next year’s cash flow, as in Step 5.

Final checklist

  • Year 0 is negative and is added outside NPV().
  • Cash flows are after-tax cash, including resale value, without financing or depreciation.
  • The manual check (sum of discounted cash flows) equals NPV.
  • IRR and NPV give the same decision against the hurdle rate.
  • Irregular dates use XNPV and XIRR.
  • Payback is within the project’s life.
Practice file: Download the NPV, IRR and payback calculator. Replace the yellow cash flows and the rate with your own project.